This year's annual summer contracted paving bid was approved last month. Work on the following roadways will start on Tuesday, 7/5/2022.
· Oak Street: 1st St to 6th St
· Shryock Avenue: 4th St to 6th St
· Chestnut Street: 2nd St to 6th St
No parking signage will be placed up on Friday (7/1) but will not take effect until 7/5/2022.
The work will consist of milling for a couple days, then paving the following week. Work is expected to last for two weeks and traffic will be directed in the area while work is underway.